progress of construction
Construction progress December 2021
In December, the following works were performed at the construction site of the OLEGIVSKIY multifunctional complex:
Section 1:
Foundation construction - 10%.
Section 2:
Pit excavation - 100%.
Pile field device - 100%.
Section 3:
Pile field arrangement - 80%.
Section 4:
Pile field arrangement - 70%.
Section 5:
Pile field device - 60%.
Parking:
Construction of the foundation for a tower crane - 100%.
Pile field device - 30%.
Stay tuned