progress of construction
Construction progress for February 2022
In February, the following works were performed on the construction site of BFC Olegivskiy:
Section 1:
- Arrangement of foundations - 100%;
- Backfill arrangement - 100%;
- The device of a power plate - 60%.
Section 2:
- Arrangement of foundations - 100%;
- Backfill arrangement - 100%;
- The device of a power plate - 20%.
Section 3:
- Arrangement of foundations - 50%;
- Backfill arrangement - 50%.
Section 4:
- Arrangement of foundations - 47%;
- Backfill arrangement - 50%.
Section 5:
- Arrangement of the pile field - 100%;
- Arrangement of foundations - 55%;
- Backfill arrangement - 40%.
Parking:
- Arrangement of the pile field - 100%;
- Arrangement of foundations - 13%;
- Backfill arrangement - 8%.
Stay tuned
Other news
Promotions
We give guaranteed discounts on apartments!
6/16/2022
News
Club house OLEGIVSKII joined the lending program from CRYSTALBANK
2/18/2022
News
Start of sales of parking in the club house OLEGIVSKII
2/15/2022
progress of construction
Construction progress for January 2022
2/1/2022