Construction progress for February 2022

In February, the following works were performed on the construction site of BFC Olegivskiy:

Section 1:

  • Arrangement of foundations - 100%;
  • Backfill arrangement - 100%;
  • The device of a power plate - 60%.

Section 2:

  • Arrangement of foundations - 100%;
  • Backfill arrangement - 100%;
  • The device of a power plate - 20%.

Section 3:

  • Arrangement of foundations - 50%;
  • Backfill arrangement - 50%.

Section 4:

  • Arrangement of foundations - 47%;
  • Backfill arrangement - 50%.

Section 5:

  • Arrangement of the pile field - 100%;
  • Arrangement of foundations - 55%;
  • Backfill arrangement - 40%.

Parking:

  • Arrangement of the pile field - 100%;
  • Arrangement of foundations - 13%;
  • Backfill arrangement - 8%.

Stay tuned

Other news

  • Promotions

    Choose an apartment in the OLEGIVSKIY club house on exclusive terms!

    9/30/2022

  • Promotions

    Buy an apartment without risks

    9/28/2022

  • progress of construction

    Construction progress for August 2022

    9/23/2022

  • News

    Club house OLEGIVSKII joined the lending program from CRYSTALBANK

    2/18/2022