Construction progress for January 2022

In January, the following work was carried out at the construction site of the MFC Olegivskiy:

Section 1:

  • Excavation - 100%;
  • Pile field arrangement - 100%;
  • Construction of foundations - 90%;
  • Backfill device - 70%.

Section 2:

  • Sheet piling - 100%;
  • Construction of foundations - 30%;
  • Backfill device - 20%.

Section 3:

  • Excavation - 100%;
  • Pile field arrangement - 100%.

Section 4:

  • Excavation - 100%;
  • Pile field arrangement - 95%.

Section 5:

  • Excavation - 100%;
  • Pile field arrangement - 60%.

Parking:

  • Excavation - 100%;
  • Arrangement of a pile field for a tower crane - 100%;
  • Pile field arrangement - 60%.

Stay tuned

Other news

  • Promotions

    Choose an apartment in the OLEGIVSKIY club house on exclusive terms!

    9/30/2022

  • Promotions

    Buy an apartment without risks

    9/28/2022

  • progress of construction

    Construction progress for August 2022

    9/23/2022

  • progress of construction

    Construction progress for February 2022

    2/22/2022