progress of construction

Construction progress for November 2021

In November, the following works were performed on the construction site of BFC OLEGIVSKYI:

Section 1:

Development of the pit - 100%;

Arrangement of the pile field - 50%.

Section 2:

Installation of sheet piling - 100%;

Development of the pit - 100%.

Section 3:

Installation of sheet piling - 100%;

Development of the pit - 100%.

Section 4:

Installation of sheet piling - 100%;

Development of the pit - 100%.

Section 5:

Development of the pit - 100%;

Arrangement of the pile field - 50%.

Parking:

Development of the pit - 95%.